Created by Frescon

Be a SociaLight and  Follow Us:

  • White Facebook Icon
  • White Twitter Icon
  • White Instagram Icon
  • White YouTube Icon

VISUAL CONTROL TOWER, AIRPORT

DUBLIN

This project has been completed as part of a tender project. However, in this case we produced this 4D animation using Navisworks Manage to emphasise the more technical side of the project.

It is always a good idea to work within Navisworks Manage when the construction programme is being developed and several construction sequence options need to be analysed.

Not only does it illustrate the exact construction methodology but also the logistical issues and solutions for this complex project. Work at such height involves an extensive amount of logistical planning.

We’re very happy that we were able to support our client on this tender and had played a part in winning the job.

Date: 2016